Housing and Urban-Rural Development Bureau (Project Construction Committee) of each district and city, and all relevant units:
Since this year,For effective prevention and controlCOVID-19 epidemic, part of the project construction.adoptprevention and controlmeasureLead to an increase in costs,According to the Civil Code of People’s Republic of China (PRC) and relevant laws and regulations, according to the principle of risk sharing, the cost of prevention and control of COVID-19 epidemic in construction projects is calculated.Formulate the following guiding standards:
First, the cost of epidemic prevention and control in COVID-19 is composed of the cost of normalization of epidemic prevention and control in COVID-19 and the increased cost of epidemic prevention and control in COVID-19. COVID-19 epidemic normalization prevention and control fee is in accordance with the "Notice on Printing and Distributing the Guidelines for Normalization of Epidemic Prevention and Control of Housing Municipal Works" (Su Jian letter quality safety [2021〕606No.) Cost of measures implemented.;The increase fee for epidemic prevention and control in COVID-19 is based on the normalized epidemic prevention and control measures, and special measures are taken due to the dynamic epidemic prevention and control in various places.butIncreased costs.
Two, COVID-19 epidemic normalization prevention and control fees.Provided by the contractor to the employer.normalizationAfter the epidemic prevention and control plan is approved by the employer, the project fee shall be borne by the employer as a total price measure.If there is an agreement in the contract, it shall prevail.
Prevention and control of epidemic normalization in COVID-19feeSee the annex for the items in the bill of quantities and the reference rates.
Three, COVID-19 epidemic prevention and control costs as an abnormal, unexpected expenses, mainly including the content and the principle of cost bearing are as follows:
(1)shouldExpenses borne by the Employer
1. According to the requirements of epidemic prevention and control, the wages of necessary management personnel and security personnel during the construction site shutdown;
2. According to the requirements of epidemic prevention and control, the construction site will be stopped and then resumed, and the project cleaning and repair costs after the resumption of work;
3. Self-funded detection expenses and round-trip transportation expenses incurred by increasing the frequency of nucleic acid detection;
4. Strengthen disinfection and increase epidemic prevention management at the construction sitepersonnelIncrease the cost of distributing epidemic prevention materials;
5. The epidemic prevention and control department requires that managers and workers from low-risk areas to the project location be isolated, the isolation costs incurred and the wages of personnel during the isolation period.;
6. After the time limit for a project is postponed, if the Employer requests to rush the work, the rush-time expenses incurred.
(two) the cost shared by the employer and the contractor through consultation
1. In addition to the necessary management personnel and security personnel, the wages of the management personnel and workers of other construction enterprises during the period when the epidemic prevention and control site is shut down and closed at the construction site;
2. According to the requirements of epidemic prevention and control, the mechanical stagnation, turnover materials and temporary facilities during the construction site shutdown;
3. Due to traffic control, materials, equipment, machinery and personnel cannot enter the site in time, and the increased frequency of nucleic acid detection takes up construction time, resulting in efficiency reduction expenses on the construction site;
4. Due to traffic control, the transportation of materials and equipment is limited, which occurs.Traffic controlAccess fees at intersections.
(3) The contractor shall keep records of the actual expenses and costs incurred by the enterprise, collect written supporting materials, and apply for visas in time. Management fees and profits are not included in the valuation.suitTender down rate. For the negotiated share, the proportion borne by the Employer shall not be less than50%The principle of pricing. During the period of isolation, shutdown and slowdown, the salary standard of personnel shall be in accordance with the "Jiangsu Province Salary"payRegulations "provisions.
(four) COVID-19 epidemic prevention and control fees included in the increase.otherThe project fee only includes taxes.
Fourth,becauseIf the epidemic prevention and control policy is strengthened and the construction period is affected,According to the following principlesPostpone:
1. The number of days of work stoppage at the construction site is calculated according to the time of work stoppage and resumption required by epidemic prevention and control, and the construction period is postponed. Due to the contractor’s epidemic prevention and control plan is not in place, can’t return to work in time caused by the delay, shall be borne by the contractor.
2. If the materials, equipment, and personnel can’t enter the site in time and the frequency of nucleic acid detection increases, which leads to the slowdown of the construction site and the inefficiency of the construction, the contracting parties shall negotiate to determine the number of days to postpone the construction period according to the specific conditions of the project.
V. RightIn case of possible price fluctuation of labor, materials, equipment and machinery, both contracting parties shall implement it in accordance with the relevant clauses of price adjustment agreed in the contract.
Six, shelter hospital, etc.epidemic prevention and controlEmergency construction projects should be adopted.useCost plus remunerationForm of contract. When determining the project cost, we should fully consider the impact of a large number of concentrated inputs of labor, materials and machinery on the cost, as well as the costs of epidemic prevention and control, speeding up work and reducing efficiency.
Seven, thisGuiding standardIt shall come into force as of the date of promulgation. Our province is under construction and planned to be built.And has been completed but not completed.Construction project, cost calculation and construction period of epidemic prevention and control in COVID-19adjustCan refer to thisGuiding standardExecute. Municipalities can formulate specific implementation measures according to the actual situation in the region. This is not applicable to projects that have been completed and settled.Guiding standard.
Attachment: 1. Bill of Quantities for Prevention and Control of Epidemic Normalization in COVID-19. pdf
2. COVID-19 epidemic normalization prevention and control fee charging standard table. pdf
Jiangsu Provincial Department of Housing and Urban-Rural Development
twenty22yearsevenmoon11sun
(This piece is released publicly.)